JET GROUT PROGRESS
JG Dashboard
Based on Site Record
OPEN JG REALTIME PROGRESS↗CURRENT PROGRESS8.48%
GRAPH PERIODREFERENCE DATE · SITE RECORD UNTIL 04 AUG 2026
CURRENT PERFORMANCE
Actual Rig · Completion · Cement Ratio
ACTUAL / COMPLETED9.5 / 7 Nos.LAST 60 DAYS · THROUGH 04 AUG 2026
ACTUAL RIG / COMPLETION (Nos.)
CEMENT RATIO (%)
543210
125%100%75%50%25%0%
TARGET 97–110%
Actual Rig (Nos.)Completion (Nos.)Cement Ratio (%)
CURRENT ACCUMULATION
Accumulated Grout Volume & Completed Cycle
271.61 m³TOTAL GROUT
COMPLETED (Nos.)
GROUT VOLUME (m³)
86420
300 m³180 m³60 m³0 m³
Completed (Nos.)Accumulated Grout Volume
PLANNING SCENARIO
Estimated Construction Completion Date
Preliminary forecast based on Site Record production · 6-day workweek.
EST. COMPLETION05 OCT 2026
Current rig · 2 Nos./day